The Federal Airport Authority of Nigeria and Julius Berger, the contractor handling the repair of Nnamdi Azikiwe International Airport, Abuja runway, have said the work is 40 per cent completed.
The duo gave made this known in Abuja on Monday when members of the House of Representatives Committee on Aviation, led by its Chairman, Nkeiruka Onyejeocha, inspected the project.
Yemi Ayelesan, the Resident Engineer, FAAN, told the committee that the hardest part of the work, which is mailing of the 3.6km runway, had been completed.
He explained that the laying of ‘’fibre glide rubber”, which prevents water from going deep underground and also prevent runway from cracking, has also been completed.
Ayelesan told the committee that the contractors are working to specifications and would deliver on schedule, expressing confidence that the six weeks period for reopening of the airport was feasible.
According to him, the contractors are working round the clock to ensure that they meet the deadline.
Ayelesan said the repair work was a total reconstruction and not partial rehabilitation, explaining that the entire runway had been excavated for laying of asphalt.
He said there were isolated areas that were so bad that required digging deeper beyond mailing and laying of asphalt, stating that the entire surface were mailed to a certain depth.
According to him, there is nothing like partial rehabilitation, even the taxi way is being repaired.
Ayelesan saidL “Laying asphalt does not take time; it is the easiest part of the work.
“The lighting system is the next step, and the cable can be fixed within two days.
“As things are now, we will start fixing the light cable on March 29.”
Dr. Lai’s Richter, the Project Manager, Julius Berger, said the work was being done in line with the programme of work.
Richter said the fixing of the lighting cable would commence on Wednesday, restating that the runway repairs would be completed the before April 19 deadline.
Onyejeocha said their visit was to seek explanation on the level of work so far in line with the project agreement.
She also raised concern as to whether the repair work was a total reconstruction or partial repair, urging the contractor to ensure the completion of the project as scheduled.
“We want them to know that Nigerians are concerned and that there should be no extension of the completion date based on the agreement that we have put in place,” she said.
The contractors have recorded progress within 19 days since the commencement of work.
The runway was shut on March 8 for six weeks for its total repair and Abuja flights diverted to Kaduna pending the completion of the repair work.
트레져스 오브 아즈텍
평범한 한린이라도 구석에 서 있을 수밖에 없다.
https://community.windy.com/user/beachturkey13
머니 마리아치(인니티니티 릴스)
술레이만 황제가 이집트에 도착했을 때 수많은 사람들이 환호하기 시작했습니다.
포춘 슬롯
이제… 많은 사람들이 기쁨으로 빛나기 시작했습니다.
슬롯 무료 쿠폰
Zhu Wenjing은 평소처럼 운전사를 만나러 왔고 여전히 밖에서 기다리고있었습니다.
슬롯 무료
가장 말문이 막힌 것은 그의 어리석은 아들이 실제로 따랐다는 것입니다.
mvp 토토 사이트
게다가 이 스웨터를 입으면 굉장히 덥게 느껴진다.